Happy New Year to all Mako shareholders.

We end 2020 with our mine ready to be turned on in the New Year.

The goals for 2021 are:

Commercial Production in Q2

Resource delineation drilling at Las Conchitas

1st ever regional drilling program

Exciting year ahead!
$mko.v

Mining back in action!

Still only mined 2.5 benches of HG as we focus on stripping at about 20% of full capacity (to save $ pre-prod).

First 2 benches > 0.5 Oz/t!

Last 1/2 bench was caught in the great fire assay backlog of 2020. Should get those back next week.
$mko.v

Footings for tailings press done — last major piece that needs to be installed

LOTS of piping & connections being welded inside

Based on grades of bench above, that bus is sitting on a very valuable parking lot! I’ll report the 1/2 bench next week (week after latest).
You can follow @AkibaLeisman.
Tip: mention @twtextapp on a Twitter thread with the keyword “unroll” to get a link to it.

Latest Threads Unrolled:

By continuing to use the site, you are consenting to the use of cookies as explained in our Cookie Policy to improve your experience.