@BILD was give exclusive access to email conversations & internal documents of the BSH - the Federal Agency for Maritime Navigation and Hydrography - which is responsible for the #NordStream2 construction permits in Germany’s EEZ by @Umwelthilfe🙏🏼.
The documents prove that a @NordStream2 lawyer intervened in the permission process of the federal agency in October (by email!), turning a formal “change authorization” to continue building the pipeline in December 2020 into an informal “approval” of the company’s application.
As a result of the changed permit character, environmental organizations and other third parties became legally unable to challenge the BSH permit and stop the construction work in December. Something, @ConstZerger of the @Umwelthilfe called “a Christmas present to #NordStream2.
Right now, the BSH still is in the permission process to continue #NordStream2 construction work beyond Dec 31 in Germany’s EEZ.
Environmental organizations challenged this & it’s officially an “open process”.
However, in an email from Dec 3, the agency promised to the German ...
Infrastructure Ministry that #NordStream2 will receive its construction permission before the end of December - which makes the whole process a sham as the decision was already (politically) made, but is not published.
You can read the entire article here:
https://www.bild.de/politik/ausland/politik-ausland/nord-stream-2-russen-anwaelte-kippen-amts-entscheid-74596984.bild.html
You can follow @JulianRoepcke.
Tip: mention @twtextapp on a Twitter thread with the keyword “unroll” to get a link to it.

Latest Threads Unrolled:

By continuing to use the site, you are consenting to the use of cookies as explained in our Cookie Policy to improve your experience.