2. Hwange Thermal Power Station expansion.

A US$1.5 billion project funded by China.

This one is a Giga-Deal.

The deal will see the completion of Units 7 & 8, adding 600 MW to the grid

It started in 2018 is now 40% complete.

More than 2000 people employed!!
👇👇🏼👇🇿🇼🇿🇼🇿🇼
3. Robert Gabriel Mugabe International Airport expansion

This is another Mega Deal... A US$150 million project for the expansion of the Harare International Airport.

Work is ongoing & ahead of schedule.

It's a FACT! Hundreds of people employed.

FACT, not Fiction
4. The Darwendale Project

This is a US$4.2 billion deal for the establishment of a Platinum mine by Great Dyke Investments.

It's a Joint Venture between Zimbabwe & Russia.

Equipment is on site, excavation has started, building the mine ongoing. 5000 jobs to be created!👇🏼👇🇿🇼🇿🇼
5. The Karo Resources Deal

Another US$4.5 billion Platinum Mining Deal.

The project started in 2018 & is at a very advanced state. 15 000 jobs to be created directly, 90 000 indirectly. So far, 2500 people employed.

Will include a 600 MW Power Station.

FACT, not FICTION
6. New Parliament Building

Another US$100 million project funded by the Chinese govt.

This is a grant given to Zimbabwe by China.

The project is WAY AHEAD of schedule.

Hundreds of people employed directly & indirectly.

Another US$100 million FACT!!!
7. Beitbridge Border Post Modernisation

This is a US$239 million project that will see the expansion & modernisation of the Beitbridge Border Post.

President @edmnangagwa launched the project in July 2018.

Construction is already underway.

Jobs, Jobs, Jobs!

FACT!
8. The Kazungula Bridge Project

The Kazungula Bridge, a US$161 million project, was gonna see traffic diverted from Zimbabwe, thus loss of revenue.

President @edmnangagwa got Zim incorporated into the project with Botswana & Zambia.

It's almost complete, we will benefit!
9. Conclusion.

President @edmnangagwa's govt saw the implementation of almost all the Mega Deals signed.

The US$4 billion Batoka Gorge Hydro Power Plant is being implemented.

Real people got jobs. If u didn't get a job, don't say it's fiction, IT'S NOT!

Asante

🇿🇼🇿🇼🇿🇼🇿🇼
You can follow @KMutisi.
Tip: mention @twtextapp on a Twitter thread with the keyword “unroll” to get a link to it.

Latest Threads Unrolled:

By continuing to use the site, you are consenting to the use of cookies as explained in our Cookie Policy to improve your experience.